GMW Connections Project Waaia 2

project commencement date: April 2020

Project Budget

$0.86M

Project Location

Waaia (Vic)

Overview:

  • Installation of new 500m MV 12/6 & MV3/12/6 Principal Pipeline (DN900-DN630) and fittings.
  • Installation of new 1.4 km MV 2/13/6 Principal Pipeline (DN800-DN500) and fittings.
  • Supply and Installation of 4 new Stock and Domestic Outlets on principal pipeline.
  • Construction of German, Williams and Graham on Farm Works Packages.
  • Supply and installation of 2no. Type B channel off take structures.
  • Decommission and removal of 6 Dethridge wheel meters and associated outlet structures.
  • Site reinstatement.

Related Projects

Driving progress across Southeast Queensland

View Projects

    Noosa (QLD)

    Noosa Landfill Western Batter Missing link Capping and RRA Pad Project

    Gympie (QLD)

    Station Road Signalisation Project

    Gympie (QLD)

    Water Network Water Main Renewal Project D&C

    Caloundra (QLD)

    Gagalba P18 sewer pumpstation

    Mundubbera (QLD)

    Mundubbera Landfill Expansion Project

    Gympie (QLD)

    G3 Pumpstation Relocation Project

    Gympie (QLD)

    Southside Sewer Stage 9 & 10

    Gympie (QLD)

    G1 Pump Station Relocation Project

    Gympie (QLD)

    Bonnick Road Eastern Cell Landfill Project